Sunday, 25 October 2015

25th October.... 1 week to go.

All righty then.... we are hitting the final straight.... and getting ready to move back in. !!!

Finally !!!

The retaining wall is in and backfilled.
The wall has over 3 tons or cement, water, gravel and sand in it.. .There is 2 tons of back fill gravel behind it. ... so that's not going anywhere and is finally all finished.

Cleared up the skip and front yard.
Got the drainage in around the back.
Put a clothesline in and a letter box.

Next week the move is on!











Sunday, 18 October 2015

18th of October - Countdown is one - 2 weeks to go.....

Update for this week.

We have the Carpet in the house this is last thing to do inside before moving in...

The guys  filled the concrete into the retaining  walls. No new photos of that, but got the retaining walls completed for the back yard. Just the deck to go in now.

I planted the 75 litre tree lilly pilly...









Saturday, 10 October 2015

10th of October... Driveway finished and retaining wall in ...

Ok... so the driveway is finished .... finally ...

The retaining wall went in today... pretty much done in a day....

So first shot is the dum ass council not allowing for a flowing driveway.
We need to change this and will after the council sign off on it....



Retaining wall starting out...


Shot of the drive and super builder Dennis.


The guys bricking up the side of the pool


I dug this out today... so stoked i work in an office usually...

Retaining walll




8th of October driveway continues ....

Originally the driveway was meant to be done in a week ... so much for that ... week 2 and still not done.....

There is still a long way to go. '''

Photo of the steps with non slip treads 


Close up of the concrete carly chose brush to the edge....


The speckled look as the concrete dries... we need to appy a sealer 

Close up of the front door and the front entrance. 

 Super Jake running over the double strength reo -

Foyer a day later.

Photo of the side path ... 
 I have filled in behind the laundry door
 Dug out under the pool...
Hey i found the return points.

James and i dug out the area for the new pool pump.... now all i got to do is move the bastard !


Cleared out the plants from the back of the yard ... it was 36 degrees this weekend., ...

Quick shot of the driveway more to come!


1st of October - Driveway formwork and side path

The driveway is taking longer than expected
The rock is a bit harder than expected.

We have teh side path laid in baby poo brown concrete.