While we were away over the easter break we have had progress in a few areas.
We have
1. Got the roof on .
2. Got the stairs in - internal
3. Bricks have been cleaned down.
The roof looks the goods ! - We have been hit with really crap weather so again delays are kicking in.
Bricks have been cleaned and look really good.
Internal Stairs are now in ...
View of teh back of the house.
Close up of the roof ...
Internal shot of the insulation.
Tuesday, 21 April 2015
Thursday, 16 April 2015
Still waiting for roofing ... 2nd April - Preeaster
Limited progress again this week. This post is from the 2nd of April.
Progress made this week.
The roof struts are complete for the front balcony and and the back deck area.
Shot of the balcony showing the roofing struts over the top of the balcony.
Shot from the street - you can start to see the size of the house
Progress made this week.
The roof struts are complete for the front balcony and and the back deck area.
Shot of the balcony showing the roofing struts over the top of the balcony.
Shot from the street - you can start to see the size of the house
Saturday, 21 March 2015
22nd March Bricking is continuing
Bricking up to the second level is now just about done.
Hopefully hte roof is going on soon.
Rear Columns are complete
View from the back of the house.
View down the side of the house looking at the pantry door.
Internal Brick work is progressing.
Looking back through the house. Will be good once the roof is on.
Inter Brick work looking at the laundry.
Hopefully hte roof is going on soon.
Rear Columns are complete
View from the back of the house.
View down the side of the house looking at the pantry door.
Internal Brick work is progressing.
Looking back through the house. Will be good once the roof is on.
Inter Brick work looking at the laundry.
Sunday, 15 March 2015
March 15 Roof trusses and scaffolding
Roof trusses are on and scaffolding for brick work is up.
Trusses were delivered you can see them stacked upstairs.
Scaffolding was delivered last week ( weekending the seventh ) and stacked out the front.
View from the street - the house starts to look imposing.
Carly Sussing out here kitchen area.
View frmo the balcony back over the house and into the scaffolding.
Bedroom windows.
Living room windows.
Another shot from the street with the trusses on.
Close up of the scaffold
Trusses were delivered you can see them stacked upstairs.
Scaffolding was delivered last week ( weekending the seventh ) and stacked out the front.
Bricks were stacked on the other side of the road.
View from the master bedroom over the park .
View from the street - the house starts to look imposing.
A forste of roof trusses.
Carly Sussing out here kitchen area.
View frmo the balcony back over the house and into the scaffolding.
Bedroom windows.
Living room windows.
Another shot from the street with the trusses on.
Close up of the scaffold
Sunday, 1 March 2015
March 1st - Balcony and Roof Preparation
Ok .. So Balcony has now been poured. The roof trusses have been delivered .
Hopefully we can get a crack on and start to see some quick progress.
Trusses stacked in the front yard
Balcony looking over the park.
Trusses over the Driveway.
The balcony is going to rock!
Hopefully we can get a crack on and start to see some quick progress.
Trusses stacked in the front yard
Balcony looking over the park.
Trusses over the Driveway.
The balcony is going to rock!
Friday, 20 February 2015
Friday, 6 February 2015
Feb 2015 Second floor frames
Ok so house is taking shape now.
Second floor frames are up. Next step is to pour concrete for balcony
Second floor frames are up. Next step is to pour concrete for balcony