14th of December - Frames have been erected. It only took a day - Saturday the 13th they erected them. Hoping the bricky will start next week .
Bricks have arrvived - Emerald bricks from Boral.
Do these look the same colour as the sample brick? I Think so.
All that reamins of the frame to be put up .
That shows the front door - nice and wide.
Oops - noggin is bit wonky
That is the door into the under section of the house. May be years to come i might excavate to another room .
View from the back yard
Shows where the alfresco will move back to.
View out over the park.
Windows in the entertainment room. They look pretty cool .
Close up on the brick .
Saturday, 13 December 2014
Sunday, 7 December 2014
Frames have been delivered
The Frames were delivered on Thursday 4th december - hopefully it will start going up this week.
Looks like there will be pleant of space under the house.
You can see the land now looks level. and the corner is well dug out.
Looks like there will be pleant of space under the house.
You can see the land now looks level. and the corner is well dug out.
Tuesday, 2 December 2014
December 2nd Drainage is in
The drainage has been excavated around the slab and backfilled in.
You can see the access from the driveway to the garage looks good and that a car will fit.
Looks as though more has been taken out of the corner.
Shot of the corner again - the dual track shows should be able to get a car in there -
Need to get a retaining wall in under the fence. I think the gap will be about 600. I expect it to be flat around the side and may need to be concreted.
Need to have retaining wall on top of the exposed sandstone - and a small retaining wall for the drop down to the slab,
View showing the angle of the driveway - looks good now and hopefully the columns are at an even base level
This is the RHS of house - all back-filled and drainage as shown
Close up photos of the Concrete fill for the bakc half of the house.
Shows the height of the underfloor area.
You can see the access from the driveway to the garage looks good and that a car will fit.
Looks as though more has been taken out of the corner.
Shot of the corner again - the dual track shows should be able to get a car in there -
Need to get a retaining wall in under the fence. I think the gap will be about 600. I expect it to be flat around the side and may need to be concreted.
Need to have retaining wall on top of the exposed sandstone - and a small retaining wall for the drop down to the slab,
View showing the angle of the driveway - looks good now and hopefully the columns are at an even base level
Close up photos of the Concrete fill for the bakc half of the house.
Shows the height of the underfloor area.
Monday, 24 November 2014
23rd November Slab has been laid
Slab is laid.
Shots of the slab - foreground is the garage and the back area is the study and entertainment room.
This shot shows the height difference between the columns and the concern is how excavate down to get the drive way in
Slab on the garage side of things - the garage feel like it will be huge.
Shot of the slab.
This shot shows the height difference between the columns and the concern is how excavate down to get the drive way in
Slab on the garage side of things - the garage feel like it will be huge.
Shot of the slab.
Excavations on going 15th of november.
Excavations are now progressed and the foundations around the back of the house and the framework has been put up around the slab. Noted that there is a lot of excess fill back on the site.
Also that there is still a slope back into the slab area from the front yard.
Formwork for the slab .
Trench for foundations around the back of the house.
Trench for the foundations.
Another shot of the form work.
Note the water seepage from the RHS.
Shot showing the formwork.
The corner has been excavated out a little bit.
Also that there is still a slope back into the slab area from the front yard.
Formwork for the slab .
Trench for foundations around the back of the house.
Trench for the foundations.
Another shot of the form work.
Note the water seepage from the RHS.
Shot showing the formwork.
The corner has been excavated out a little bit.
Excavations on going 16th November
Weekend of the 15th of November
Digger has been called back and the excavation is more pronounced
The aggregate has been place in the driveway as well.
Mainparts are that the land is cleared and the excavation for the foundations are not yet in.
The corner has been removed a little bit ... more needs to be done.
The excavation down the side of the house is complete - it is going to be a tight squeeze to get this excavated and a retaining wall in.
Close up shot of the corner and the height difference from the slab ... more on this when the slab is laid.
You can see the split level where the slab is being stepped up from the garage to the ground floor level. Note again the height of the corner section.
Note again the gradient into the house.
Digger has been called back and the excavation is more pronounced
The aggregate has been place in the driveway as well.
Mainparts are that the land is cleared and the excavation for the foundations are not yet in.
The corner has been removed a little bit ... more needs to be done.
The excavation down the side of the house is complete - it is going to be a tight squeeze to get this excavated and a retaining wall in.
Close up shot of the corner and the height difference from the slab ... more on this when the slab is laid.
You can see the split level where the slab is being stepped up from the garage to the ground floor level. Note again the height of the corner section.
Note again the gradient into the house.
Getting the excavation correct - 10th November
Ok.
So the digger has been called back on site to do some more work.
You can see in the first couple of photos that the cut at the back of the yard is not as deep or pronounced as further on.
These photos are from the Weekend of 10th of November.
Note here that the corner was to be dug out and you can see the slop back into the slab area.
The digger is actually on the left hand side of this phot and you can see the cut into the Alfresco area at the back of the block and the cut in along the front of the pool.
Digger on the side where the garage is all of this fill is removed.
Shot showing the slope back into the cut area for the slab.
This photos shows raised corner section note that the foundations for the pillars are not in yet.
So the digger has been called back on site to do some more work.
You can see in the first couple of photos that the cut at the back of the yard is not as deep or pronounced as further on.
These photos are from the Weekend of 10th of November.
Note here that the corner was to be dug out and you can see the slop back into the slab area.
The digger is actually on the left hand side of this phot and you can see the cut into the Alfresco area at the back of the block and the cut in along the front of the pool.
Digger on the side where the garage is all of this fill is removed.
Shot showing the slope back into the cut area for the slab.
This photos shows raised corner section note that the foundations for the pillars are not in yet.