We went through for a pre inspection before handover.
Impressed that Montgomery use an independent consulting firm to review and provide defects prior to us being in the house.
The house had a whole heap of orange dots where the consultants had picked up defects.
We only picked out about 3 or 4 additional defects.
Kudos to montgomery homes for the way they handled handover
Photos as below.
Saturday, 5 September 2015
1st of July
The house is at lock up stage so the posts have slowed down.
We got in on the first of july.
Key updates.
Kitchen Bench Tops are in
Tiling is in progress.
Doors have been delivered and are being hung
We got in on the first of july.
Key updates.
Kitchen Bench Tops are in
Tiling is in progress.
Doors have been delivered and are being hung
Saturday, 20 June 2015
June 21st
The house is now at lock up stage.
Things are moving along quite quickly now.
Doors and skirting are all on
Window frames are on
Kitchen cabinets are in ..
Vanities are in
Bath was being installed while we were there
Tiles to go in next week!
Things are moving along quite quickly now.
Doors and skirting are all on
Window frames are on
Kitchen cabinets are in ..
Vanities are in
Bath was being installed while we were there
Tiles to go in next week!
Monday, 8 June 2015
June 8th
Progress again this week.
The plastering has been finished off, looks like most gyprocking is now done.
The front door is in.
All the internal doors ahve been delivered and the skirting boards.
The plastering has been finished off, looks like most gyprocking is now done.
The front door is in.
All the internal doors ahve been delivered and the skirting boards.
Subscribe to: