Sunday, 27 September 2015

29th September - Driveway excavation

Excavation for the drive way and retaining wall has been started.
Major messy job, rock is very tough, getting there

Excavation used a small digger and finished the job with a rock saw.

This was shows the before and after photos of the rock excavation. The rock at the top is the excavation from the side of the house.






Photos showing the excavation from the side of the house are below.





excavation from the driveway as below.











13th September - Tiles laid

Tiles were laid this week.








Monday, 7 September 2015

7th Sept - Flooring update

Flooring update.

Floor was laid on the weekend, engineered prefinished blackbutt.
Getting ready for the tiles to be laid this week.
1 minor plumbing issue in the backyard/ 

Cement sheets for stabilisation have been laid as a foundation for the tiles 
Rumpus room wiht only back lights on.


 Hallway and landings


 Blackbutt laid upstairs.






Plumbing down pipe was cracked and with water pressure from the tank - we got a geyser.


Saturday, 5 September 2015

5th Sept First retaining wall

We go the keys and this weekend was all about the retaining wall on the south side of the house.




Sunday 30th AUugst

WOOOOOTTTTT!!!!!

Keys have been handed over
Spent the weekend of the 29th and 30th of August putting in downlights.








29th July Pre Handover inspection

We went through for a pre inspection before handover.
Impressed that Montgomery use an independent consulting firm to review and provide defects prior to us being in the house.

The house had a whole heap of orange dots where the consultants had picked up defects.
We only picked out about 3 or 4 additional  defects.

Kudos to montgomery homes for the way they handled handover

Photos as below.